K0372 K372: Ensure smoke barriers are constructed to a 1 hour fire resistance rating.
E

Deficiency in Smoke Barrier Wall Construction

New Gouverneur Hospital S N FNew York, New York Survey Completed on 12-31-2024

Summary

The facility failed to ensure that smoke barrier walls were constructed to provide at least a one-half-hour fire resistance rating as required by NFPA 101. During a Life Safety Code recertification survey, surveyors observed deficiencies in the smoke barrier walls on two of the eight resident floors. Specifically, on the 13th Floor adjacent to resident room 1314, there was an opening of approximately 1/8 inch around a 1-inch metal pipe. Additionally, on the 11th Floor adjacent to resident room 1126, a penetration of approximately 4 inches by 4 inches was found. These observations indicate that the smoke barrier walls were not adequately sealed to restrict the transfer of smoke, as required by the relevant fire safety codes. The Director of Maintenance acknowledged the issue during an interview at the time of the observation, noting that the pipe would be sealed with fire stop material. However, the report does not provide details on any corrective actions taken at the time of the survey.

Plan Of Correction

Plan of Correction: Approved January 31, 2025 K372 Smoke Barrier Walls 1. What Corrective Action(s) will be accomplished for those residents found to have been affected by the deficient practice: The opening observed in the smoke barrier wall of approximately 1/8 inch around a 1-inch metal pipe on the 13th Floor adjacent to resident room 1314 was sealed with a fire stop material. The opening observed in the smoke barrier wall of approximately 4 inches x 4 inches on the 11th Floor adjacent to resident room 1126 was sealed with a fire stop material. 2. How will you identify other residents having the potential to be affected by the same deficient practice and what corrective action will be taken: An audit of all smoke barrier walls throughout the facility was conducted to ensure all openings are correctly sealed with fire stop material. 3. What measures will be put in place or what systemic changes you will make to ensure that the deficient practice does not recur: A system for a regular review of the smoke barrier walls was developed. The Director of Maintenance will oversee the sealing of the openings and the audit of the smoke barrier walls. 4. How the Corrective Action(s) will be monitored to ensure the deficient practice will not recur, i.e., what quality assurance program will be put into practice: The Director of Maintenance/Designee will gather the data from the audit of the smoke barrier walls and report findings to the QAPI Committee for a period of 3 months to ensure the smoke barrier walls are compliant. 5. Responsible Individual: Director of Maintenance

Penalty

No penalty information released
tooltip icon
The penalty, as released by CMS, applies to the entire inspection this citation is part of, covering all citations and f-tags issued, not just this specific f-tag. For the complete original report, please refer to the 'Details' section.
See other K0372 citations
Improper Repair of Smoke Barrier Penetrations in Multiple Smoke Compartments
E
K0372 K372: Ensure smoke barriers are constructed to a 1 hour fire resistance rating.
Short Summary

Surveyors found that smoke/fire-rated enclosures were not properly maintained, with penetrations in smoke barriers in several general storage rooms across multiple smoke compartments. The Maintenance Director stated that insulation and fiberglass were used to pack and cover these holes but could not confirm that the materials were approved for fire-rated construction. Inspectors observed penetrations covered with fiberglass and noted a hole in one fiberglass panel in a storage room, resulting in a deficiency under NFPA 101 requirements for smoke barrier construction.

No penalty information released
tooltip icon
The penalty, as released by CMS, applies to the entire inspection this citation is part of, covering all citations and f-tags issued, not just this specific f-tag. For the complete original report, please refer to the 'Details' section.
Unsealed Penetrations in Smoke/Fire Barriers After Electrical Work
E
K0372 K372: Ensure smoke barriers are constructed to a 1 hour fire resistance rating.
Short Summary

Surveyors found that smoke/fire barriers in three of fourteen smoke compartments, including the hot water room, the barrier between the kitchen and a smoke compartment, and the smoke wall leading to the Alzheimer’s unit, had penetrations that were not properly fire-stopped. During the on-site interview, the Maintenance Director acknowledged that recent electrical work had been completed and that the contractor failed to seal these penetrations, resulting in noncompliance with NFPA 101 smoke barrier construction requirements.

No penalty information released
tooltip icon
The penalty, as released by CMS, applies to the entire inspection this citation is part of, covering all citations and f-tags issued, not just this specific f-tag. For the complete original report, please refer to the 'Details' section.
Unsealed Penetration in Smoke Barrier Wall
E
K0372 K372: Ensure smoke barriers are constructed to a 1 hour fire resistance rating.
Short Summary

A deficiency was identified when an unsealed penetration around data wires was observed in a smoke barrier wall on the second floor near the Rehabilitation Department. This issue was confirmed by the Administrator and Maintenance Director and affected one of two floors.

No penalty information released
tooltip icon
The penalty, as released by CMS, applies to the entire inspection this citation is part of, covering all citations and f-tags issued, not just this specific f-tag. For the complete original report, please refer to the 'Details' section.
Unprotected Penetration in Smoke Barrier Wall
E
K0372 K372: Ensure smoke barriers are constructed to a 1 hour fire resistance rating.
Short Summary

An unprotected penetration was found in a smoke barrier wall above double doors near the ADON/Medical Records Office, where blue and red wires passed through without proper protection. This issue, confirmed by the Director of Maintenance, affected two of twelve smoke compartments.

No penalty information released
tooltip icon
The penalty, as released by CMS, applies to the entire inspection this citation is part of, covering all citations and f-tags issued, not just this specific f-tag. For the complete original report, please refer to the 'Details' section.
Unsealed Wire Penetrations in Smoke Barrier
E
K0372 K372: Ensure smoke barriers are constructed to a 1 hour fire resistance rating.
Short Summary

Surveyors found that two wires passed unsealed through a smoke barrier above the ceiling near a resident corridor, with the Maintenance Director confirming unawareness of the sealing requirement. This deficiency had the potential to affect five residents and did not comply with NFPA 101-2012 standards for smoke barrier construction.

No penalty information released
tooltip icon
The penalty, as released by CMS, applies to the entire inspection this citation is part of, covering all citations and f-tags issued, not just this specific f-tag. For the complete original report, please refer to the 'Details' section.
Failure to Maintain Smoke Barrier Integrity per NFPA 101
E
K0372 K372: Ensure smoke barriers are constructed to a 1 hour fire resistance rating.
Short Summary

Surveyors found multiple penetrations in smoke barriers sealed with non-fire-rated materials and one unsealed pipe, compromising the required fire and smoke resistance in several corridors and the attic. Maintenance leadership confirmed uncertainty about the materials used, and these deficiencies had the potential to affect all 39 residents.

No penalty information released
tooltip icon
The penalty, as released by CMS, applies to the entire inspection this citation is part of, covering all citations and f-tags issued, not just this specific f-tag. For the complete original report, please refer to the 'Details' section.
Citation search

Search every citation & Plan of Correction

Go to search
Citation watch

Track new serious citations across New York

Get a heads-up on the newest immediate-jeopardy (J–L) citations in New York — where surveyors are focused right now.

Free · about one email a month

Trusted data from CMS and state health departments

Every citation, penalty and Plan of Correction is sourced from public CMS records (latest release July 29, 2026) and official state health department websites — never guesswork.

In your survey window? See what surveyors are citing.

The Survey-Prep Report maps your facility's risk from 12 months of CMS and state citation data — what's being cited around you and what to check first. $129 one-time.

Get the Survey-Prep Report
An unhandled error has occurred. Reload 🗙