Average — CMS composite of the measures below.
The next survey window likely opens around December 2026
Estimate from public CMS data, current as of July 2026. Survey timing is at the state agency's discretion.
Citation history
Health deficiencies cited at Logan Square Rehabilitation And Healthcare Center during CMS and state inspections, most recent first.
Unsanitary Food Handling Practices: Dietary staff were observed handling ready-to-eat food without gloves and preparing resident meals without proper hair nets or beard coverings. The FSD confirmed staff are expected to wear the required PPE and that the facility does not currently use use-by or discard-by dates on prepared or opened food items.
Missing State Survey Agency Contact Postings: Required DOH contact information was not posted in prominent, readily accessible locations on two nursing units. During a tour, both the 2nd- and 3rd-floor units had no required posting, and the only sign found in the dining room listed a DOH field office number that was actually for Building Safety Inspection. The NHA and DOSS confirmed the unit bulletin boards had been removed during renovations.
Failure to Use Required PPE During EBP Care A resident with a feeding tube, a resident with toe wounds, and a resident with venous/arterial ulcers were all on EBP with signage posted outside their rooms requiring gowns and gloves for high-contact care. During feeding tube medication administration, wound care, and a bed bath, staff wore gloves only and did not don gowns as required by policy. The IP/DON confirmed staff had been educated on PPE use but acknowledged that staff do not always follow the EBP requirements.
A resident was transferred to the hospital after a fall, but the written transfer notice given to the resident and representative did not include all required regulatory details, including the specific reason for transfer and other required information in understandable language. The ADON confirmed the notice was incomplete and stated this was not consistent facility practice.
Medications were found at a resident's bedside during a survey observation, including a round orange pill and a round white pill next to a pill cup. An LPN identified the pills as aspirin and a bromide tablet and removed them to the med cart. The resident had Parkinson's disease, vertebral artery dissection, spinal stenosis, and hyperlipidemia, and the facility failed to prevent the bedside medication hazard.
Failure to follow up on consultant pharmacist MRR recommendations affected two residents. One resident received an antipsychotic medication without an allowable supporting diagnosis, and the record showed no resolution of the irregularity. Another resident had a PRN diclofenac gel order that the pharmacist said needed clarification on the amount and administration instructions, but the MAR/record did not show the order was updated after the MD response.
A resident’s pharmacy review identified duplicate acetaminophen orders, and the prescriber response was to discontinue the 325 mg dose and continue the 500 mg dose for pain. However, the clinical record showed the 500 mg order was discontinued while the 325 mg order remained active, and the DON confirmed the incorrect dose had been discontinued.
The facility did not maintain its fire alarm system properly, as evidenced by multiple trouble codes displayed on the fire alarm panel. This issue was confirmed by the Executive Director of Construction and Ancillary Services.
The facility failed to maintain its automatic sprinkler system, with missing tests and inspections, and improper installation issues. A 3-year full flow trip test and a 4th quarter 2024 inspection were not conducted. Data wires were strapped to a sprinkler pipe, and a sprinkler was missing its escutcheon. These issues were confirmed by the Executive Director of Construction and Ancillary Services.
The facility failed to maintain and inspect its HVAC systems, specifically the fire/smoke dampers, as they could not provide documentation of an inspection within the past four years. This deficiency was confirmed during an interview with the Executive Director of Construction and Ancillary Services.
The facility failed to maintain and inspect the emergency generator, affecting the entire facility. Documentation for monthly battery testing, an annual 90-minute load bank test, and an annual fuel quality test was missing. The Executive Director confirmed the absence of these records, indicating non-compliance with NFPA standards.
The facility failed to maintain accurate portable Life Safety Code Floor Plans, missing critical details such as smoke and fire barrier walls, horizontal exits, and rated rooms. This deficiency was confirmed during an interview with the Executive Director of Construction and Ancillary Services.
The facility did not maintain and inspect portable fire extinguishers as required by NFPA 10 standards. A document review revealed the absence of a certificate for the technician conducting annual inspections. This issue was confirmed during an interview with the Executive Director of Construction and Ancillary Services.
The facility failed to ensure corridor doors could resist smoke passage, as observed on the third floor near a resident room. The metal door frame had open penetrations, compromising safety standards. This was confirmed by the Executive Director of Construction and Ancillary Services.
The facility failed to maintain smoke barrier walls free of unsealed penetrations, compromising the required 1/2-hour fire resistance rating. Observations revealed penetrations around data wires and a sprinkler pipe in the basement near the upper garage elevator. This was confirmed by the Executive Director of Construction and Ancillary Services.
The facility failed to maintain the fire resistance rating of its trash chute system on the second floor. The trash chute door did not close and latch properly when tested, as confirmed by the Executive Director of Construction and Ancillary Services.
The facility failed to maintain electrical wiring protection in the main garage electrical room, where multiple panels were missing circuit breaker protective blanks. This was confirmed by the Executive Director of Construction and Ancillary Services.
The facility did not conduct required testing of non-hospital grade electrical receptacles at patient bed locations within the mandated 12-month intervals. The testing should have included visual inspection, polarity verification, and grounding blade retention force checks. This deficiency was confirmed during an interview with the Executive Director of Construction and Ancillary Services, who acknowledged the absence of necessary documentation.
An extension cord was improperly used to power a personal refrigerator in a resident's room, violating NFPA standards. The Executive Director confirmed the issue during an exit interview.
Logan Square Rehabilitation And Healthcare Center failed to review and update their Emergency Preparedness Plan annually, as required by federal regulations. This deficiency was identified during a survey, with no signatures confirming the plan's review or update. The issue was acknowledged by the Executive Director of Construction and Ancillary Services.
The facility failed to include required names and contact information in its Emergency Preparedness Plan. A document review revealed the absence of contact details for staff, service entities, patients' physicians, other facilities, and volunteers. The Executive Director confirmed the omission during an exit interview.
The facility's Emergency Preparedness Plan was found deficient as it lacked contact information for the State Licensing and Certification Agency and the Office of the State Long-Term Care Ombudsman. This was confirmed during a document review and an exit interview with the Executive Director of Construction and Ancillary Services.
The facility failed to maintain documentation of initial and annual Emergency Preparedness training for staff and volunteers, affecting the entire facility. A document review revealed the absence of records demonstrating staff knowledge of emergency procedures, confirmed by the Executive Director during an exit interview.
The facility failed to conduct the required two exercises to test the emergency preparedness plan, affecting the entire facility. A document review revealed that the facility did not perform the necessary exercises within the previous 12 months, and this was confirmed during an exit interview with the Executive Director of Construction and Ancillary Services, who acknowledged the lack of documentation.
The facility failed to label the date of opening on multi-use eye drops on two medication carts, as observed during a med pass. This oversight was confirmed by interviews with the responsible licensed nurses, violating the facility's policy on medication labeling.
Two residents experienced discomfort due to inadequate bed sizes in the facility. One resident, who is 6 feet 3 inches tall, had their feet pressing against the footboard, causing numbness and fear of falling due to the narrow bed width. Despite a maintenance request for a bed extender, the issue persisted. Another resident was observed with their foot on the footboard, indicating the bed was too short. Interviews confirmed the facility's failure to provide appropriate accommodations.
The facility failed to protect residents' privacy when a registered nurse was overheard relaying a resident's vital signs aloud in a room with multiple residents and staff, violating privacy protocols.
A facility failed to provide a written summary of the baseline care plan to a resident and their representative, which should have included initial goals, physician orders, therapy services, and social services. The resident, admitted with a progressive neurological condition, stroke, and Parkinson's disease, and their family were unaware if all medications were being administered. The Social Service Director confirmed that a baseline care plan meeting was not conducted, and a written summary was not provided.
A facility failed to ensure the administration of Warfarin for a resident with polycythemia vera and atrial fibrillation. The resident's medication was not administered on multiple occasions due to pharmacy delays, and there was no documentation of the pharmacy being contacted or the physician being informed, as required by facility policy.
A resident with severe cognitive impairment and a history of stroke was not provided with the prescribed adaptive eating utensils during a meal, despite a physician's order and facility policy requiring such equipment. The resident's family and a nurse aide confirmed the oversight.
The facility failed to ensure the Director of Nursing (DON) attended nine consecutive Quality Assurance Process Improvement (QAPI) meetings from February to October 2024. The absence was confirmed by regional staff, and documentation for July 2024 was missing, indicating a deficiency in meeting regulatory requirements for the QAPI committee.
The facility failed to offer influenza immunizations to two residents upon admission, despite their willingness to receive the vaccine. Both residents, who were cognitively intact, reported not being offered the vaccine, and their clinical records lacked documentation of the offer, administration, or refusal of the immunization.
The facility failed to provide a sanitary and comfortable environment for two residents. One resident's IV pole was found soiled with old tube feeding formula, while another resident had to endure a broken over-the-head light that could not be turned off, despite staff attempts to fix it. The latter resident, admitted with a progressive neurological condition, had been sleeping with the lights on since admission.
A facility failed to accurately assess a resident's catheter status. The resident, admitted with an indwelling catheter due to several medical conditions, was incorrectly documented in the MDS as not having a catheter. This error was confirmed by the DON.
A resident was mistakenly discharged due to an incorrect calculation of Medicare benefits, and the facility failed to provide the required Notice of Medicare Non-Coverage (CMS 10123), which would have informed the resident of their right to appeal the denial of Medicare services.
Unsanitary Food Handling Practices
Penalty
Summary
The facility failed to ensure sanitary food handling practices were followed by dietary staff during food preparation and service. During observations in the main kitchen, a dietary aide was seen handling ready-to-eat food without gloves, two staff members were preparing food without hair nets, one dietary aide wore a hair net that did not fully cover all hair, and another dietary aide wore a beard covering that did not fully contain facial hair while engaged in food preparation. Additional dietary aides were observed in the kitchen without hair nets during active preparation and handling of resident meals. The Food Service Director confirmed that staff are expected to wear hair nets, beard or facial hair coverings as applicable, and gloves when handling food, and also confirmed that the facility does not currently use or indicate use-by or discard-by dates on prepared or opened food items.
Missing State Survey Agency Contact Postings
Penalty
Summary
The facility did not ensure that required State Survey Agency contact information was posted in prominent and readily accessible locations on two nursing units. During a tour with the Director of Social Services, the Second-Floor nursing unit was observed on January 12, 2026 at 10:00 a.m. and the Third-Floor nursing unit was observed on January 12, 2025 at 10:15 a.m.; on both units, there was no posting for the required Department of Health contact information. On each unit, the dining room had a standard-size page posted on the door that read "DOH Field Office Contact Information 610 270 3485," but a search revealed that this number was for the Department of Health Building Safety Inspection. The facility's Resident Rights policy, revised February 2011, states that residents have rights to voice grievances, have the facility respond to grievances, examine survey results, and communicate with outside agencies, including state surveyors and the state long-term care ombudsman. The Nursing Home Administrator stated at 10:13 a.m. that the sign had been up in the building since the last survey in January 2025, and the Director of Social Services and the Nursing Home Administrator confirmed at 10:15 a.m. that there were no postings for the required Department of Health contact information on either nursing unit because the units were under renovation and the bulletin boards had been taken down.
Failure to Use Required PPE During Enhanced Barrier Precautions
Penalty
Summary
The facility failed to ensure proper infection prevention and control practices for three residents who were subject to Enhanced Barrier Precautions (EBPs). Resident R31 had diagnoses including CVA and malnutrition and required a feeding tube; the record showed physician orders for EBPs every shift, and signage outside the room indicated staff were to wear gowns and gloves during high-contact activities, including feeding tube care and wound care. During observation of medication administration via the feeding tube, a licensed nurse used a syringe and flush while wearing gloves and a mask only and did not wear a gown as required by the facility policy. Resident R20 had impaired skin integrity related to arterial ulcers on the toes and feet, with EBPs required during wound care. Although EBP signage was posted on the room door, a licensed nurse provided wound care to the resident's toe while wearing gloves only and not a gown. Resident R95 had venous and/or arterial ulcers and physician orders for EBPs; signage on the room door indicated gowns and gloves were required during high-contact care. During a bed bath, a nursing assistant wore gloves only and did not wear a gown, and stated the EBP sign was not intended for the resident. The Assistant Director of Nursing/Infection Preventionist stated staff had been educated on infection control and PPE use, confirmed that wound care, personal care, and feeding tube medication administration require gowns and gloves, and acknowledged that staff do not always follow these requirements.
Incomplete Written Transfer Notice
Penalty
Summary
The facility failed to ensure that Resident R112 and the resident’s representative received a written transfer notice containing all required regulatory details after the resident was admitted to the hospital following a fall. Review of the medical record showed documentation that a notification was provided, but the written notice did not specify the required elements, including the detailed reason for the transfer and other required regulatory information, in a manner and language the resident or representative could understand. During interview, the Assistant Director of Nursing confirmed that the written notification provided for the transfer did not include the required details, and further stated that it is not facility practice to ensure transfer notices consistently contain all required regulatory elements.
Medications Left at Bedside
Penalty
Summary
The facility failed to ensure prevention of accidents and hazards related to medications found at the bedside for one resident. Facility policy titled, "Administer Medications," states medications are to be administered in a safe and timely manner as prescribed, and that if a resident is not available to receive medication during the pass, the MAR may be flagged and the nurse is to return after completing the pass to administer the missed medication. During an observation on the third-floor nursing unit, a surveyor found a round orange pill on the resident's bedside table next to a white plastic pill cup. The resident was interviewed at the time of the observation. The nurse was alerted and came to the room, where she visualized the orange pill and then moved items on the bedside table and found one additional round white pill. The two pills were placed in the pill cup and taken to the medication cart. The nurse identified the medications as an aspirin tablet and a bromide tablet. The resident had diagnoses including Parkinson's disease, dissection of the vertebral artery, spinal stenosis, and hyperlipidemia.
Failure to Follow Up on Pharmacist Medication Review Recommendations
Penalty
Summary
The facility failed to ensure timely and effective follow-up of consultant pharmacist medication regimen review recommendations for two residents. The facility policy required a licensed consultant pharmacist to review each resident’s medication regimen at least monthly, identify medication irregularities, and report non-life-threatening irregularities in writing to the physician within three business days, with physician responses documented in the medical record. Review of the records showed that these requirements were not met for two residents reviewed. For one resident, the clinical record showed an order for Risperdal (risperidone) 2 mg by mouth at bedtime for anxiety, and the consultant pharmacist’s medication regimen review identified that the resident was receiving an antipsychotic medication without an allowable supporting diagnosis. The record contained no evidence that the irregularity was resolved. For another resident, the clinical record showed an order for Diclofenac Sodium 1% topical gel to the left arm and thigh every eight hours as needed for pain, and the consultant pharmacist recommended clarifying the order to specify the amount to be applied and to include administration instructions to prevent medication errors. Although the physician responded, the medical record showed no evidence that the order was modified to include the recommended clarifications.
Incorrect acetaminophen order discontinued after pharmacy review
Penalty
Summary
Accurate documentation related to pharmacy reviews was not maintained for one resident. The Consultant Pharmacist’s Medication Monthly Review recommendation for the resident noted duplicate acetaminophen orders for 500 mg and 325 mg for mild pain and asked that the duplicate order be discontinued if appropriate, or that the total mg dose be added to each order if both were to be given concurrently. The physician/prescriber response indicated that the 325 mg dose should be discontinued and the 500 mg dose continued for scale 1-4 pain. However, review of the resident’s clinical record showed that the acetaminophen 500 mg order was discontinued and the 325 mg order remained active. The DON confirmed that the incorrect acetaminophen dose had been discontinued.
Fire Alarm System Maintenance Deficiency
Penalty
Summary
The facility failed to maintain its fire alarm system in proper operating condition, which affected the entire facility. During an observation on January 21, 2025, at 10:45 a.m., it was noted that the fire alarm panel displayed multiple trouble codes. This issue was confirmed during an exit interview with the Executive Director of Construction and Ancillary Services on the same day at 1:15 p.m.
Plan Of Correction
ED of construction to in-service the Maintenance staff of proper reading of the fire panel and report any trouble alarms immediately to their Supervisor. The Facility is working with the current Vendor (Johnson Controls) and an additional Vendor (Independence) to make repairs or replace the aged fire panel so trouble alarms stop randomly reporting. Due to the difficulty of parts or replacement of the fire panel, the Facility is requesting a 120-day time-limited waiver. The fire panel will be audited daily with a record of any current trouble signals recorded until repairs are completed. TLW request sent via email. Johnson Control letter sent to center and forwarded to DOH stating that they estimate that work can be completed 90 days from March 7th 2025 which June 5th 2025. If further extension is required center will update doh with further correspondence from Johnson Controls.
Sprinkler System Maintenance Deficiencies
Penalty
Summary
The facility failed to maintain its automatic sprinkler system, affecting the entire facility. During observations and document review on January 21, 2025, several deficiencies were identified. The facility did not conduct a 3-year full flow trip test of the dry automatic sprinkler system, and the 4th quarter 2024 sprinkler inspection was missing. Additionally, data wires were improperly strapped to the ceiling sprinkler pipe in the basement next to the upper garage elevator. Furthermore, a sprinkler in the 3rd floor Activities closet was missing its escutcheon. These deficiencies were confirmed during an exit interview with the Executive Director of Construction and Ancillary Services.
Plan Of Correction
ED of construction to Inservice supervisor of Plants Operations on policy and procedure ensuring sprinkler system maintained. All items A-D have been completed; 4th quarter report received after surveyor departed. Supervisor of Plants Operations or delegate to complete 3x per week x 4 weeks all items A-D to ensure compliance. Supervisor of Plant Operations or delegate to complete audits 3x per week x 4 weeks to compliance with policy and procedure. Audit findings will be submitted to QAPI committee monthly for review and recommendations as needed.
Failure to Inspect HVAC Fire/Smoke Dampers
Penalty
Summary
The facility failed to maintain and inspect its HVAC systems, specifically the fire/smoke dampers, affecting the entire facility. During a document review on January 21, 2025, it was found that the facility could not provide documentation of a fire/smoke dampers inspection performed within the past four years. This deficiency was confirmed during an exit interview with the Executive Director of Construction and Ancillary Services on the same day.
Plan Of Correction
ED of construction to Inservice supervisor of Plants Operations on policy and procedure on smoke dampers. Damper inspection was completed by facility on 11-06-2024. Supervisor of Plant Operations or delegate to complete audits 3x per week x 4 weeks to compliance with policy and procedure. Audit findings will be submitted to QAPI committee monthly for review and recommendations as needed.
Failure to Maintain and Inspect Emergency Generator
Penalty
Summary
The facility failed to maintain and inspect the emergency generator, which affects the entire facility. During a document review on January 21, 2025, it was found that the facility could not provide documentation for several critical tests and inspections. These included the monthly testing of battery electrolyte specific gravity or conductance testing, an annual 90-minute load bank test, and an annual fuel quality test. An exit interview with the Executive Director of Construction and Ancillary Services confirmed the absence of the required documentation. This lack of documentation indicates that the facility did not adhere to the necessary maintenance and testing protocols for the emergency generator as outlined by NFPA standards, potentially compromising the facility's ability to provide essential power in emergencies.
Plan Of Correction
- ED of construction to Inservice supervisor of Plant Operations on ensuring generator battery testing, fuel samples and 90 min load. - Fuel test, load bank and battery conductance testing. - Director of Plants Operations or delegate to complete audits 3x per week x 4 weeks to ensure generator battery testing and fuel quality sample and 90 min load test is completed. Audit findings will be submitted to the QAPI committee monthly for further review and recommendations as needed. - Further audit frequency will be determined based on the outcome of the previously completed audit findings.
Inaccurate Life Safety Code Floor Plans
Penalty
Summary
The facility was found to be deficient in maintaining accurate portable Life Safety Code Floor Plans. During a document review, it was observed that the floor plans did not include essential information such as smoke barrier walls, fire barrier walls, horizontal exits, and rated rooms like storage rooms, soiled utility rooms, and designated medical gas rooms. Additionally, required exits and shaft walls were not clearly noted on the plans. This deficiency was confirmed during an exit interview with the Executive Director of Construction and Ancillary Services.
Plan Of Correction
1) Facility obtained accurate floor plans. 2) ED of construction to Inservice on policy and procedure for ensuring the safe storage of floor plans. 3) Supervisor of Plant Operations or Delegate to complete audits 3x per week x 4 weeks to ensure plans are completed and available in accordance with policy and procedure.
Failure to Maintain and Inspect Portable Fire Extinguishers
Penalty
Summary
The facility failed to maintain and inspect portable fire extinguishers in accordance with NFPA 10 standards, affecting the entire facility. During a document review, it was discovered that the facility could not provide a certificate for the technician responsible for conducting the annual fire extinguisher inspections. This deficiency was confirmed during an exit interview with the Executive Director of Construction and Ancillary Services, who acknowledged the missing documentation.
Plan Of Correction
- ED of construction to Inservice supervisor of Plant Operations on policy and procedure for portable fire extinguishers. Document was received after surveyor exited. - Supervisor of Plant Operations or delegate to complete audits 3x per week x 4 weeks to ensure compliance. Audit findings will be submitted to QAPI committee monthly for further review.
Deficiency in Corridor Door Smoke Resistance
Penalty
Summary
The facility failed to ensure that doors protecting corridor openings could resist the passage of smoke, which is a requirement for safety in long-term care facilities. This deficiency was observed on the third floor, specifically at the double doors near resident room 310. The doors were found to have a metal door frame with open penetrations above the closer, which compromises their ability to prevent smoke from passing through. During an exit interview with the Executive Director of Construction and Ancillary Services, it was confirmed that the metal door frame had penetrations. This issue affects one of the twenty-four floors in the facility, indicating a lapse in maintaining the required safety standards for corridor doors, particularly in smoke compartments.
Plan Of Correction
ED of construction to Inservice supervisor of plants operations on policy and procedure regarding corridor doors. Door closures will be installed in the same open mounting holes at top of frame to ensure smoke doesn't pass. Supervisor of Plant Operations to conduct audits 3x per week x 4 weeks to ensure all corridor doors are smoke tight in accordance with policies and procedures. Supervisor of Plant Operations or delegate to complete audits 3x per week x 4 weeks to compliance with policy and procedure. Audit findings will be submitted to QAPI committee monthly for review and recommendations as needed.
Unsealed Penetrations in Smoke Barrier Walls
Penalty
Summary
The facility failed to maintain smoke barrier walls free of unsealed penetrations, which is a requirement for ensuring a 1/2-hour fire resistance rating. During an observation on January 21, 2025, at 10:55 a.m., it was noted that in the basement, next to the upper garage elevator, there were penetrations around data wires and a sprinkler pipe. This deficiency was confirmed during an exit interview with the Executive Director of Construction and Ancillary Services on the same day at 1:15 p.m.
Plan Of Correction
- ED of construction to Inservice supervisor of Plant Operations on policy and procedure for maintaining smoke barrier walls. - Penetration filled using 3M fire barrier sealant FD 150 + Red color and CP 25 WB+. - Supervisor of Plant Operations or delegate to complete audits 3x per week x 4 weeks to compliance with policy and procedure. - Audit findings will be submitted to QAPI committee monthly for review and recommendations as needed.
Trash Chute Door Fails to Close and Latch
Penalty
Summary
The facility failed to maintain the fire resistance rating of its trash chute system, specifically on the second floor. During an observation on January 21, 2025, at 12:20 p.m., it was noted that the trash chute door did not close and latch properly when tested. This deficiency was confirmed during an exit interview with the Executive Director of Construction and Ancillary Services at 1:15 p.m. on the same day.
Plan Of Correction
- ED of construction to Inservice supervisor of Plant Operations on policy and procedures for trash, laundry chutes. - Trash chute replaced. - Supervisor of Plant Operations or delegate to complete audits 3x per week x 4 weeks to ensure compliance of chute doors policy and procedure. - Supervisor of Plant Operations or delegate to complete audits 3x per week x 4 weeks to compliance with policy and procedure audit findings will be submitted to QAPI committee monthly for review and recommendations as needed.
Electrical Panel Deficiency in Main Garage
Penalty
Summary
The facility failed to maintain the protection of electrical wiring, specifically in the main garage electrical room. During an observation, it was noted that multiple electrical panels were missing a circuit breaker protective blank. This deficiency was confirmed during an exit interview with the Executive Director of Construction and Ancillary Services.
Plan Of Correction
- ED of construction to Inservice Supervisor of Plants Operations on policy and procedure for electrical panels. - Replaced open breakers with circuit breaker protective cover. - Supervisor of Plant Operations or delegate to complete audits of main electrical room 3x per week x 4 weeks to ensure compliance. - Supervisor of Plant Operations or delegate to complete audits 3x per week x 4 weeks to compliance with policy and procedure. - Audit findings will be submitted to QAPI committee monthly for review and recommendations as needed.
Failure to Test Electrical Receptacles at Patient Bed Locations
Penalty
Summary
The facility failed to ensure that electrical receptacles at patient bed locations were tested as required. During a document review, it was found that non-hospital grade receptacles were not tested at intervals not exceeding 12 months, as mandated. The testing should have included a visual inspection of physical integrity, verification of correct polarity of the hot and neutral connections, and ensuring the retention force of the grounding blade was not less than 4 oz. This deficiency was confirmed during an exit interview with the Executive Director of Construction and Ancillary Services, where it was acknowledged that the necessary documentation for these tests was missing.
Plan Of Correction
- ED of construction to Inservice supervisor or Plants Operation on policy and procedure for testing electrical receptacles. - Electrical receptacle test completed. - Supervisor of Plant Operations or delegate to complete audits 3x per week x 4 weeks to compliance with policy and procedure. Audit findings will be submitted to QAPI committee monthly for review and recommendations as needed.
Improper Use of Extension Cord in Resident Room
Penalty
Summary
The facility was found to be in violation of electrical safety standards as evidenced by the improper use of an extension cord in a resident's room. During an observation on January 21, 2025, at 12:45 p.m., it was noted that an extension cord was being used to power a personal refrigerator in a resident's room on the third floor. This use of an extension cord is not compliant with the National Fire Protection Association (NFPA) standards, which prohibit the use of extension cords as a substitute for fixed wiring. The Executive Director of Construction and Ancillary Services confirmed the presence of the extension cord during an exit interview on the same day at 1:15 p.m.
Plan Of Correction
- ED of construction to Inservice supervisor of Plant Operations on policy and procedure of power cords, extension cords and power strips. - Extension cord removed from room #331. - Director of Plants Operations or delegate to complete audits 3x per week x 4 weeks to ensure Power cords, extension cords and power strips audit is completed. Findings will be submitted to the QAPI committee monthly for further review and recommendations as needed. Further audit frequency will be determined based on the outcome of the previously completed audit findings.
Deficiency in Annual Review of Emergency Preparedness Plan
Penalty
Summary
Logan Square Rehabilitation And Healthcare Center was found to have a deficiency related to their Emergency Preparedness Plan during an Emergency Preparedness Survey conducted on January 21, 2025. The survey revealed that the facility failed to ensure that their Emergency Preparedness Plan policies and procedures were reviewed and updated at least annually, as required by 42 CFR 483.73(a). This deficiency affects the entire facility, as the plan is crucial for ensuring readiness in the event of an emergency. During the document review, it was noted that there were no signatures provided to confirm the annual review or update of the Emergency Preparedness Plan. This was acknowledged during an exit interview with the Executive Director of Construction and Ancillary Services, indicating a lapse in the facility's compliance with federal regulations. The lack of an updated emergency plan could potentially impact the facility's ability to respond effectively to emergencies, although the report does not specify any immediate consequences or risks.
Plan Of Correction
1) EPP reviewed and signed. 2) ED of construction to Inservice Plant Operations supervisor policy and procedure on how to review and update EPP annually. 3) Supervisor of Plant Operations or Delegate to complete audits 3x per week x 4 weeks to ensure compliance with policy and procedure audits to be submitted to quality assurance performance improvement committee monthly for further review. Further audit frequency will be determined based on the outcome of the previously completed audit findings.
Deficiency in Emergency Preparedness Plan
Penalty
Summary
The facility was found to be deficient in developing an Emergency Preparedness Plan that included the required names and contact information. During a document review on January 21, 2025, it was revealed that the facility's plan did not contain or reference the necessary contact information for staff, entities providing services under arrangement, patients' physicians, other facilities, and volunteers. This omission was identified as a failure to comply with the regulatory requirements for emergency preparedness communication plans. An exit interview with the Executive Director of Construction and Ancillary Services confirmed that while a contact information template was included in the Emergency Preparedness Plan, it lacked the specific names and contact information of facility-based individuals. This deficiency indicates that the facility did not meet the mandated standards for maintaining an up-to-date and comprehensive communication plan, which is essential for effective emergency preparedness.
Plan Of Correction
1) Updated communication plan and list completed by facility. 2) ED of construction to inservice supervisor of plant OPS on policy and procedure of keeping communications plan and list up to date. 3) ED of construction or delegate to complete audits 3x per week x 4 weeks to ensure communication plan and list are completed in accordance with policies and procedures. Audits findings will be submitted to QAPI committee monthly for further reviews and recommendations as needed. Further audits frequently will be determined based on the outcome of the survey.
Emergency Preparedness Plan Lacks Required Contact Information
Penalty
Summary
The facility failed to ensure that its Emergency Preparedness Plan included the necessary contact information for required emergency officials. During a document review conducted on January 21, 2025, it was discovered that the plan lacked contact information for the State Licensing and Certification Agency and the Office of the State Long-Term Care Ombudsman. This omission affects the entire facility, as these contacts are crucial for effective emergency preparedness and response. An exit interview with the Executive Director of Construction and Ancillary Services confirmed the deficiency. The interview, held on the same day as the document review, further verified that the facility had not developed an Emergency Preparedness Plan that included the required contact information for the specified emergency officials. This oversight indicates a failure to comply with the regulatory requirements for maintaining an updated and comprehensive emergency communication plan.
Plan Of Correction
1) Emergency list has been updated. 2) ED of construction to inservice supervisor of Plant Operations on policy and procedure on emergency contact information. 3) Supervisor of Plant Operations or delegate to complete audits 3x per week x 4 weeks to ensure document is completed in accordance with policy and procedure.
Deficiency in Emergency Preparedness Training Documentation
Penalty
Summary
The facility was found to be deficient in maintaining documentation of initial and annual Emergency Preparedness training for staff, individuals providing services, and volunteers. During a document review conducted on January 21, 2025, it was revealed that the facility failed to provide the required documentation demonstrating that staff members had received the necessary training in emergency procedures. This deficiency affected the entire facility, indicating a systemic issue in the training program. The surveyors noted that the facility did not have records to confirm that staff and service providers were knowledgeable about emergency procedures, as required by the regulations. The lack of documentation suggests that the facility did not conduct or properly record the training sessions, which are essential for ensuring that all personnel are prepared to respond effectively in emergency situations. An exit interview with the Executive Director of Construction and Ancillary Services confirmed the absence of annual records of employee training. This acknowledgment by the facility's leadership further substantiates the deficiency, highlighting a failure in the facility's compliance with emergency preparedness training requirements.
Plan Of Correction
1) EPP Inservice of staff to be completed. 2) ED of construction to Inservice supervisor of plant operations on EPP training program policy and procedure. 3) Supervisor of Plant Operations or delegate to complete audits 3x per week x 4 weeks to ensure compliance. Audit findings will be monthly for further review and recommendations as needed. Further audits frequency will be determined based on the outcome of the previously completed audit findings.
Failure to Conduct Required Emergency Preparedness Exercises
Penalty
Summary
The facility failed to conduct the required two exercises to test the emergency preparedness plan, which affected the entire facility. This deficiency was identified during a document review conducted on January 21, 2025, at 8:45 a.m. The review revealed that the facility did not perform the necessary exercises within the previous 12 months, as mandated by the regulations. The deficiency was confirmed during an exit interview with the Executive Director of Construction and Ancillary Services on the same day at 1:15 p.m. During this interview, it was acknowledged that the documentation supporting the completion of the required exercises was not available. This lack of documentation indicates that the facility did not adhere to the regulatory requirements for emergency preparedness testing. The absence of these exercises suggests a failure in maintaining compliance with the emergency preparedness standards set forth for long-term care facilities. The facility's inability to provide evidence of conducting these exercises highlights a significant oversight in their emergency preparedness protocols.
Plan Of Correction
1) Emergency prep exercise will be completed. 2) ED of construction to Inservice Supervisor of Plant Operations on policy and procedure for ensuring proper requirements are met. 3) Supervisor of Plant Operations or delegate to complete audits 3x per week x 4 weeks to compliance with policy and procedure. Audit findings will be submitted to QAPI committee monthly for review and recommendations as needed.
Failure to Label Ophthalmic Solutions
Penalty
Summary
The facility failed to properly label medications upon opening, specifically ophthalmic solutions, on two of the three medication carts observed on the third floor. During a medication pass on January 12, 2024, it was observed that seven boxes of multi-use eye drops on medication cart one and two boxes on medication cart two did not have the date of opening labeled on them. This was confirmed through interviews with the licensed nurses, Employee E5 and Employee E6, who were responsible for the medication carts at the time of the observation. The facility's policy titled "Medication Labeling and Storage" requires that multi-dose vials that have been opened or accessed are dated and discarded within 28 days unless the manufacturer specifies a longer date for the open vial. The failure to label the date of opening on the multi-use eye drops is a deviation from this policy. The report does not mention any specific residents affected by this deficiency, nor does it provide details on any immediate consequences resulting from the oversight.
Plan Of Correction
1) Eye drops in both medication carts have been replaced and labeled correctly with date they were opened. 2) All Medication carts have been audited to ensure all eye drops have been dated upon opening. 3) Licensed nursing staff will be educated by Director of Nursing / designee on medication storage and labeling. 4) Director of Nursing / designee will conduct random audits of medication carts weekly x 3, then monthly x 2 or until compliance is met to ensure proper medication storage and labeling on medication carts. Variances will be addressed and reported to the QAA Committee.
Failure to Provide Adequate Bed Accommodations
Penalty
Summary
The facility failed to provide reasonable accommodation for the needs of two residents, R215 and R165, as required by regulations. Resident R215, who is 6 feet 3 inches tall and weighs 225 pounds, was admitted to the facility and immediately experienced discomfort due to the bed being too small. The resident's feet pressed against the footboard, causing numbness, and the narrow width of the bed left little room for repositioning, leading to fear of falling. Despite a maintenance request for a bed extender being placed shortly after admission, the resident continued to experience discomfort and fear due to the inadequate bed size. Interviews with the nursing supervisor and the nursing home administrator confirmed the issue and the ongoing efforts to obtain a bed extender. Similarly, Resident R165 was observed with their foot on the footboard and a pillow under the ankle, indicating the bed was too short. The resident reported being unable to raise the head of the bed without placing their foot on the footboard. An interview with the administrator confirmed the bed was too short for the resident and that a bed extender could be utilized. These observations and interviews highlight the facility's failure to provide appropriate accommodations for the residents' needs, as required by regulations.
Plan Of Correction
1) Resident 215 and Resident 165 were both provided appropriate bed size with appropriate length. 2) Current residents that are taller than 6ft have been audited by the Maintenance director/designee to ensure that the bed size is appropriate for resident. 3) The Maintenance Director will be educated by the Nursing Home Administrator / designee on appropriate bed size and extensions available for residents. 4) Random audits of new admission and beds that are appropriate in length are put in place to meet residents' needs. Audits will be conducted weekly x 3 weeks, then monthly x 2 or until compliance is sustained. Variances will be addressed and reported to the QAA committee.
Breach of Resident Privacy During Vital Sign Evaluation
Penalty
Summary
The facility failed to ensure the protection of residents' rights to privacy and confidentiality, as evidenced by observations and policy review. Specifically, the facility's policy titled "Confidentiality of Information and Personal Privacy" dated October 2017, mandates safeguarding the personal privacy and confidentiality of all resident personal and medical records. However, during an observation in the third-floor activity room, a registered nurse, identified as Employee E8, was overheard relaying a resident's vital signs aloud, compromising the resident's privacy. This incident involved two of the thirty residents reviewed, highlighting a breach in the facility's adherence to privacy protocols. The observation took place in a setting where eleven residents and two employees were present, further emphasizing the lack of discretion in handling sensitive medical information. The facility's failure to protect the resident's privacy in this instance is a direct violation of the residents' rights as outlined in the facility's policy and federal regulations.
Plan Of Correction
1) Employee E8 has been educated on the facility policy for Personal Privacy / confidentiality of records. 2) All residents have the potential to be affected. 3) Director of Nursing / designee will educate facility staff on the facility policy of resident personal privacy and confidentiality of records. 4) Random audits of common areas will be conducted daily x 7 days, weekly x 3 weeks then monthly x 2 or until compliance is met. Variances will be addressed and reported to the QAA committee.
Failure to Provide Baseline Care Plan Summary
Penalty
Summary
The facility failed to provide a written summary of the baseline care plan to Resident R164 and their representative, which is a requirement under §483.21(a)(3). The baseline care plan should have included initial goals based on admission orders, physician orders, therapy services, and social services. Resident R164 was admitted with diagnoses including a progressive neurological condition, cerebrovascular accident (stroke), and Parkinson's disease. Despite these conditions, there was no documented evidence that the resident or their representative received the necessary written summary of the baseline care plan. Interviews with Resident R164 and their family revealed that they were unaware if all medications were being administered, indicating a lack of communication and documentation. The Social Service Director confirmed that a baseline care plan meeting was not conducted, and a written summary was not provided to the resident or their representative. This oversight was identified during a review of clinical records and interviews, highlighting a deficiency in meeting the regulatory requirements for baseline care planning.
Plan Of Correction
1) Resident R164 and their resident representative was provided with a written summary of the baseline care plan. 2) Current residents admitted in the past 30 days will be audited to ensure compliance with baseline care plans. Any variances will be addressed. 3) Administrator / designee will educate social services staff on baseline care plan policy. 4) Social Service Director / designee will conduct audits of new admissions to ensure compliance with baseline care plans policy. Audits will be completed weekly x 3, then monthly x 2 or until compliance is met. Variances will be addressed and reported to The QAA Committee.
Failure to Administer Anticoagulant Medication
Penalty
Summary
The facility failed to provide pharmaceutical services that ensured the accurate acquiring and administering of medications for a resident, identified as Resident R34. The facility's policy on 'Unavailable Medication' requires nursing staff to contact the pharmacy, attempt to obtain the medication from the facility's automated dispensing system, notify the physician, report the expected delivery date, and obtain new orders if a medication is unavailable. However, for Resident R34, who was on anticoagulant therapy with Warfarin for blood clot prevention, these procedures were not followed. The resident's medication administration record showed that Warfarin doses were not administered on multiple occasions, with notes indicating the medication was 'awaiting pharmacy,' but there was no documented evidence that the pharmacy was contacted or that the physician was informed of the missed doses. Resident R34, who was cognitively intact and had diagnoses of polycythemia vera and atrial fibrillation, was at risk due to the missed doses of Warfarin, an anticoagulant medication. The facility's failure to ensure the availability and administration of this critical medication was confirmed through staff interviews, where a registered nurse attributed the missed medications to the pharmacy's untimely delivery. This deficiency highlights a breakdown in the facility's pharmaceutical services, as the necessary steps to address the unavailability of medication were not documented or executed, potentially compromising the resident's care.
Plan Of Correction
1) Resident 34 medication is now available from pharmacy. 2) Current residents ordered anticoagulants will be audited to ensure availability of medication from pharmacy. Variances to be addressed. 3) Director of Nursing / Designee will educate licensed nursing staff on facility medication availability policy and procedures. 4) Director of nursing / Designees will conduct audits weekly x 3, then monthly x 2 or until compliance is met to ensure compliance with med availability policy. Variances will be addressed and reported to The QAA Committee.
Failure to Provide Adaptive Eating Equipment
Penalty
Summary
The facility failed to provide adaptive eating equipment for a resident, identified as R83, who was observed during dining on the third-floor dining room. The facility's policy titled "Assistive Devices and Equipment" states that they maintain and supervise the use of assistive devices and equipment for residents, including specialized eating utensils. Recommendations for the use of such devices are based on comprehensive assessments and documented in the resident's care plan. However, during an observation of lunch, Resident R83, who had an order for buildup utensils, was given regular utensils instead. Resident R83 has a medical history that includes malnutrition, hemiplegia, aphasia, and stroke, and has been assessed with severe cognitive impairment. A physician's order dated January 4, 2024, specified the use of buildup utensils with meals. An interview with the resident's family confirmed that the resident was supposed to have special utensils but did not receive them. A nurse aide, identified as Employee E8, also confirmed that the resident was supposed to be given buildup utensils but did not receive them during the meal observed.
Plan Of Correction
1) Resident R83 was immediately provided with their assistive devices. 2) Current residents who are ordered assistive devices with meals have been audited to ensure assistive devices are available for use. 3) Dietary director / designee will educate dietary staff on ensuring assistive devices are provided to any resident indicated for such. 4) Dietary director / designee will complete random audits to ensure identified residents are provided with ordered assistive devices. Audits will be completed weekly x 3, monthly x 2, or until compliance is met. Variances will be addressed and reported to the QAA Committee.
Failure to Ensure DON Attendance at QAPI Meetings
Penalty
Summary
The facility failed to ensure that the Director of Nursing Services attended the quarterly Quality Assurance Process Improvement (QAPI) committee meetings for nine consecutive months, from February 2024 through October 2024. This was determined based on a review of the QAPI committee meeting attendees list, which consistently lacked the presence of the Director of Nursing. The absence of the Director of Nursing was confirmed by the facility's Regional Staff during a meeting on January 15, 2025. Additionally, there was no sign-in sheet or meeting minutes available for July 2024 to confirm the attendance of any required members at the QAPI meeting. The facility did not provide this documentation at the time of the survey, and a request for copies of the original QAPI sign-in sheet was not fulfilled. This lack of documentation and attendance by the Director of Nursing constitutes a deficiency in meeting the regulatory requirements for the facility's Quality Assessment and Assurance committee.
Plan Of Correction
1) QAPI meeting has been held with appropriate attendees signatures obtained. 2) Past 3 months QAPI will reviewed to determine appropriate staff members that were missing. The NHA / designee will review the past three months of QAPI meeting minutes with the Director of Nursing. 3) NHA and Director of nursing will be educated by the Regional Clinical Consultant / Designee on Facility QAPI policy and ensuring appropriate staff members present. 4) Monthly QAPI will be audited for three months for appropriate staff member attendance. Variances will be addressed and reported to the QAA Committee.
Failure to Offer Influenza Immunizations to Residents
Penalty
Summary
The facility failed to ensure that each resident was offered an influenza immunization, as required by regulations. Specifically, two residents, identified as R34 and R315, were not offered the influenza vaccine upon admission, despite being cognitively intact and willing to receive the immunization. Resident R34, admitted on December 17, 2024, confirmed during an interview that they were not offered the vaccine but expressed willingness to accept it if suggested by a physician. A review of Resident R34's clinical records showed no documentation of the offer or administration of the influenza vaccine, nor any record of refusal or medical contraindication. Similarly, Resident R315, admitted on December 11, 2024, reported not being offered the influenza vaccine upon admission and expressed a desire to receive it before discharge. The review of Resident R315's clinical records also revealed a lack of documentation regarding the offer or administration of the influenza vaccine, as well as any refusal or medical contraindication. These findings indicate a failure by the facility to comply with the regulatory requirement to offer influenza immunizations to residents, as evidenced by the absence of necessary documentation and resident interviews.
Plan Of Correction
1) Resident R34 and Resident R315 were both offered the influenza vaccine. 2) Residents admitted during the last 30 days will be audited to ensure influenza vaccine has been offered. Variances will be addressed. 3) Director of nursing / designee will educate admissions nurse, assistant director of nursing, infection preventionist, clinical nurse leads and supervisors to ensure all new residents' vaccine history is reviewed for influenza vaccine administration and offered influenza vaccine on admission if appropriate. 4) Audits will be conducted weekly x 3, then monthly x 2 on new admissions to ensure influenza vaccines are offered if appropriate, until compliance is met. Variances will be addressed, and reported to the QAA Committee.
Facility Fails to Maintain Sanitary and Comfortable Environment
Penalty
Summary
The facility failed to maintain a sanitary and comfortable environment for two residents. For Resident R220, an observation on January 15, 2024, revealed that the IV pole used for administering an antibiotic intravenously was soiled at its base with what appeared to be old tube feeding formula. This observation was made in the presence of the Director of Nursing, indicating a lapse in maintaining cleanliness of medical equipment. Resident R164 experienced discomfort due to a malfunctioning over-the-head light that could not be turned off. The resident, who was admitted on January 2, 2025, with a progressive neurological condition, cerebrovascular accident, and Parkinson's disease, reported that the light had been broken since admission. Despite attempts by facility staff to fix the light, it remained inoperable, forcing the resident to sleep with the lights on. The administrator confirmed the issue with the light on January 12, 2025.
Plan Of Correction
1) Overhead light for resident R164 was fixed. IV pole for Resident R220 was cleaned. 2) Facility wide audit of current residents who are ordered IV medication were checked for cleanliness; variances were addressed. A facility wide audit was also completed of all resident rooms to ensure that all overhead lights had strings that were appropriate in length to meet the needs of the residents. Variances were addressed. 3) Maintenance director/designee will educate maintenance department staff members on ensuring broken overhead lights are fixed timely. Housekeeping director/designee will educate housekeeping department staff members on ensuring proper cleanliness of IV poles. 4) Random room audits will be conducted weekly x 3, then monthly x 2 or until compliance is met to ensure cleanliness of IV poles and that overhead lights are in proper working order. Variances will be addressed and reported to the QAA committee.
Inaccurate Resident Assessment of Catheter Status
Penalty
Summary
The facility failed to ensure the accuracy of a resident's assessment, specifically regarding the resident's catheter status. A clinical record review revealed that a resident was admitted to the facility with an indwelling catheter due to conditions including metabolic encephalopathy, acute kidney failure, and acute pyelonephritis. Despite the presence of the catheter, the resident's Minimum Data Set (MDS) assessment, dated December 10, 2024, inaccurately indicated that the resident did not have a catheter. This discrepancy was confirmed during an interview with the Director of Nursing on January 15, 2024.
Failure to Provide Notice of Medicare Non-Coverage
Penalty
Summary
The facility failed to provide the required advanced notice, through a Notice of Medicare Non-Coverage (CMS 10123), regarding the termination of Medicare services for one of the residents. Resident R1 was admitted on February 7, 2024, for short-term rehabilitation with Medicare skilled A services. The resident was discharged on March 15, 2024, and readmitted from the local hospital on March 19, 2024, with Medicare Part A benefits. However, the facility mistakenly discharged Resident R1 on the belief that Medicare benefits were exhausted without issuing the required NOMNC form, which would have informed the resident of their right to appeal the denial of Medicare services. An interview with the Social Worker Director revealed that Resident R1 was discharged because the Medicare service benefits were thought to be exhausted. Further interviews with the Administrator and Business Director confirmed that the facility's system incorrectly calculated the remaining Medicare benefit days, leading to the erroneous discharge. The facility acknowledged that Resident R1 should not have been discharged and that the NOMNC form should have been issued if the discharge was appropriate.
What surveyors are citing around you — mapped
All 10 risk areas, ranked with evidence
Repeat citations, what's rising near you, and quality measures — ranked so department heads know exactly where to look first.
Illustrative
What surveyors actually found near you
We read the 1,829 citations issued within 25 miles in the last 12 months — including the 24 immediate-jeopardy cases — and tell you exactly what happened, in plain English, matched to your record.
Resident with a documented fall history left unattended on the patio; found on the ground with a hip fracture.
Walk-in cooler logs missing for 12 days; expired supplements in the medication room fridge.
Illustrative
A prioritized, do-first checklist
Every risk area becomes concrete audit steps drawn from real citations at facilities like yours — run them this week, before your window opens.
Illustrative
Risk indicators are statistical estimates from public CMS data — not predictions, findings, or compliance advice.
Nursing homes near Philadelphia
How nearby facilities compare on the same public inspection record.
| Facility | Distance | Overall rating | Citations, 12 mo | Serious (J–L) |
|---|---|---|---|---|
| Tucker House Nursing And Rehabilitation Center | 0.8 mi | ★★★★★ | 25 | 0 |
| Graduate Post Acute | 1 mi | ★★★★★ | 33 | 0 |
| University City Rehabilitation And Healthcare Ctr | 1.6 mi | ★★★★★ | 11 | 0 |
| Rittenhouse Post Acute | 1.7 mi | ★★★★★ | 2 | 0 |
| Fox Subacute At South Philadelphia | 2.3 mi | ★★★★★ | 6 | 0 |
Every risk area ranked, a do-first checklist, and your local survey patterns
Built specifically for Logan Square Rehabilitation And Healthcare Center.
100% money-back within 48 hours.
Trusted data, never guesswork. Every citation, penalty, rating and Plan of Correction on this page is sourced from public CMS records (latest release July 2026) and official state health department websites.