Stay Ahead of Compliance with Monthly Citation Updates


In your State Survey window and need a snapshot of your risks?

Survey Preparedness Report

One Time Fee
$79
  • Last 12 months of citation data in one tailored report
  • Pinpoint the tags driving penalties in facilities like yours
  • Jump to regulations and pathways used by surveyors
  • Access to your report within 2 hours of purchase
  • Easily share it with your team - no registration needed
Get Your Report Now →

Monthly citation updates straight to your inbox for ongoing preparation?

Monthly Citation Reports

$18.90 per month
  • Latest citation updates delivered monthly to your email
  • Citations organized by compliance areas
  • Shared automatically with your team, by area
  • Customizable for your state(s) of interest
  • Direct links to CMS documentation relevant parts
Learn more →

Save Hours of Work with AI-Powered Plan of Correction Writer


One-Time Fee

$49 per Plan of Correction
Volume discounts available – save up to 20%
  • Quickly search for approved POC from other facilities
  • Instant access
  • Intuitive interface
  • No recurring fees
  • Save hours of work
K0918
F

Failure to Maintain Essential Electrical System

Boca Raton, Florida Survey Completed on 02-04-2025

Penalty

No penalty information released
tooltip icon
The penalty, as released by CMS, applies to the entire inspection this citation is part of, covering all citations and f-tags issued, not just this specific f-tag. For the complete original report, please refer to the 'Details' section.

Summary

The facility failed to maintain and test their Essential Electrical System in accordance with NFPA 99 standards. During a record review conducted on February 4, 2025, it was identified that there was no documentation available for weekly voltage checks for two generator batteries. Additionally, there was no documentation for monthly sealed battery conductance tests for these same batteries. This lack of documentation indicates that the facility did not perform the required maintenance and testing procedures for their generator batteries. The Regional Director of Maintenance was present during the record review and acknowledged the findings. The absence of these critical maintenance records suggests a failure to adhere to the necessary protocols for ensuring the reliability and safety of the facility's emergency power systems. This deficiency was noted as a violation of the NFPA 99 and NFPA 110 standards, which are essential for maintaining the operational readiness of the facility's electrical systems.

Plan Of Correction

Corrective Actions The following actions occurred on 2/17/2025: A. The weekly generator inspection form was updated to include a battery voltage reading for both generator batteries. B. The monthly generator inspection form was updated to include a battery conductance reading for both generator batteries. Identification of Others Potentially Affected Both facility generator batteries were accounted for, so no further evaluation was needed. Systemic Changes The Maintenance Director, or designee, will continue to perform documented weekly generator inspections to include documentation of the battery voltage, and monthly generator testing to include documentation of the battery conductance testing, on an ongoing basis as part of the facility's life safety program. Quality Assurance Results of the weekly inspections and monthly battery testing will be presented at the monthly QA meetings for 3 months. If substantial compliance is not met after 3 months, monthly inspections will continue, and results will be brought to QA meetings until substantial compliance is met.