F0655 F655: Create and put into place a plan for meeting the resident's most immediate needs within 48 hours of being admitted
D

Failure to Complete Baseline Care Plan Within Required Timeframe

Jena Nursing And Rehabilitation Center, LlcJena, Louisiana Survey Completed on 06-03-2026

Summary

The facility failed to develop and implement a baseline care plan that included the instructions needed to provide effective and person-centered care within 48 hours of admission for Resident #78. Resident #78 was admitted on 05/29/2026 with diagnoses including Schizoaffective Disorder, Unspecified; Asymptomatic Human Immunodeficiency Virus; Bipolar Disorder; and Insomnia. Review of the medical record showed that Resident #78 did not have a baseline care plan. During interview, Resident #78 stated he was new to the facility and had recently been admitted. The Unit Manager stated she was responsible for completing baseline care plans, including follow-up to ensure they were completed within the required 48-hour timeframe, and confirmed that Resident #78's baseline care plan was not developed or completed within 48 hours, although it should have been.

Penalty

No penalty information released
tooltip icon
The penalty, as released by CMS, applies to the entire inspection this citation is part of, covering all citations and f-tags issued, not just this specific f-tag. For the complete original report, please refer to the 'Details' section.

Resources

Below are regulatory guidelines relevant to this citation:

See other F0655 citations
Baseline Care Plan Missing PICC Line and Contact Isolation Needs
D
F0655 F655: Create and put into place a plan for meeting the resident's most immediate needs within 48 hours of being admitted
Short Summary

A resident admitted after hospitalization for a MDR UTI was receiving IV meropenem through a PICC line and required contact isolation precautions and an indwelling catheter. Although the admission report and nurse-to-nurse handoff documented these needs, the baseline care plan did not include the PICC line or isolation precautions among the resident’s immediate care needs. Staff interviews confirmed the resident arrived with these treatments and precautions in place, and the DON stated the expectation was for a baseline care plan to be developed and implemented within 24 hours of admission.

No penalty information released
tooltip icon
The penalty, as released by CMS, applies to the entire inspection this citation is part of, covering all citations and f-tags issued, not just this specific f-tag. For the complete original report, please refer to the 'Details' section.
Baseline Care Plan Not Completed for Bed Mobility and Transfers
D
F0655 F655: Create and put into place a plan for meeting the resident's most immediate needs within 48 hours of being admitted
Short Summary

A resident admitted with traumatic subdural hemorrhage, T5-6 vertebral fractures, and respiratory failure did not have a baseline care plan with instructions for positioning, bed mobility, or transfers within 48 hours of admission. The EHR and bedside Kardex lacked guidance for nursing staff, and observations showed the resident slouching in bed and later with feet touching the lower bed frame. An LPN and the DON both stated the care plan did not meet expectations.

No penalty information released
tooltip icon
The penalty, as released by CMS, applies to the entire inspection this citation is part of, covering all citations and f-tags issued, not just this specific f-tag. For the complete original report, please refer to the 'Details' section.
Failure to Provide Baseline Care Plan Summary
D
F0655 F655: Create and put into place a plan for meeting the resident's most immediate needs within 48 hours of being admitted
Short Summary

A resident admitted with asthma, hypothyroidism, and HTN did not have evidence in the record that a written summary of the baseline care plan and order summary was provided to the resident and/or representative. The NHA confirmed the missing documentation during interview.

No penalty information released
tooltip icon
The penalty, as released by CMS, applies to the entire inspection this citation is part of, covering all citations and f-tags issued, not just this specific f-tag. For the complete original report, please refer to the 'Details' section.
Failure to Include EBP for PEG Tube in Care Plan
D
F0655 F655: Create and put into place a plan for meeting the resident's most immediate needs within 48 hours of being admitted
Short Summary

A resident with hemiplegia, severe cognitive impairment, a feeding tube, and surgical wounds was ordered EBP for a PEG tube, but the care plan did not include the EBP need or related interventions. The DON confirmed the omission and stated that the care plan is meant to communicate interventions for resident safety, protection, and care.

No penalty information released
tooltip icon
The penalty, as released by CMS, applies to the entire inspection this citation is part of, covering all citations and f-tags issued, not just this specific f-tag. For the complete original report, please refer to the 'Details' section.
Failure to Develop Baseline Care Plans Within 48 Hours
D
F0655 F655: Create and put into place a plan for meeting the resident's most immediate needs within 48 hours of being admitted
Short Summary

Failure to Develop Baseline Care Plans Within 48 Hours: The facility did not open baseline care plans within the required timeframe for three residents reviewed for abuse and falls. One resident’s abuse care plan was started well after admission and the baseline plan did not include abuse. Another resident’s abuse/neglect plan was started after an abuse allegation, and a third resident with a high fall risk score had no baseline fall care plan despite a fall and an abuse allegation after admission. The Care Plan Coordinator confirmed the baseline plans were not in place as required.

No penalty information released
tooltip icon
The penalty, as released by CMS, applies to the entire inspection this citation is part of, covering all citations and f-tags issued, not just this specific f-tag. For the complete original report, please refer to the 'Details' section.
Delayed Baseline Care Plan Completion
D
F0655 F655: Create and put into place a plan for meeting the resident's most immediate needs within 48 hours of being admitted
Short Summary

Delayed Baseline Care Plan Completion: A resident admitted with muscle weakness and a need for assistance with personal care did not have a baseline care plan completed within the required timeframe. The care plan, which should have included ADLs, nutrition, skin, pain, and fall risk, was not completed until 13 days after admission. An LPN stated the charge nurse initiated the plan on admission, and the DNS acknowledged the delay.

No penalty information released
tooltip icon
The penalty, as released by CMS, applies to the entire inspection this citation is part of, covering all citations and f-tags issued, not just this specific f-tag. For the complete original report, please refer to the 'Details' section.
Citation search

Search every citation & Plan of Correction

Go to search
Citation watch

Track new serious citations across Louisiana

Get a heads-up on the newest immediate-jeopardy (J–L) citations in Louisiana — where surveyors are focused right now.

Free · about one email a month

Trusted data from CMS and state health departments

Every citation, penalty and Plan of Correction is sourced from public CMS records (latest release July 29, 2026) and official state health department websites — never guesswork.

In your survey window? See what surveyors are citing.

The Survey-Prep Report maps your facility's risk from 12 months of CMS and state citation data — what's being cited around you and what to check first. $129 one-time.

Get the Survey-Prep Report
An unhandled error has occurred. Reload 🗙