F0924 F924: Put firmly secured handrails on each side of hallways.
D

Unsafe Handrail on Hall W

Camelot Rehabilitation At Magnolia ParkLafayette, Louisiana Survey Completed on 02-04-2025

Summary

The facility failed to ensure that hallway handrails were securely affixed to the walls in one of the six hallways observed, specifically Hall W. This deficiency was identified through multiple observations on February 2, 2025, where a handrail outside of Room A on Hall W was found broken, with one end detached from the wall and pointing outward into the hallway. An exposed screw was also noted at the end of the detached portion of the handrail. During an interview, the Maintenance Supervisor confirmed the broken and detached handrail, acknowledging that it was unsafe and should have been repaired. The facility's maintenance policy, last revised in December 2009, mandates that maintenance personnel maintain the building in compliance with laws and regulations, ensuring safety and operability at all times.

Penalty

No penalty information released
tooltip icon
The penalty, as released by CMS, applies to the entire inspection this citation is part of, covering all citations and f-tags issued, not just this specific f-tag. For the complete original report, please refer to the 'Details' section.

Resources

Below are regulatory guidelines relevant to this citation:

See other F0924 citations
Loose and Unattached Hallway Handrails
E
F0924 F924: Put firmly secured handrails on each side of hallways.
Short Summary

Loose and Unattached Hallway Handrails: Second-floor hallway handrails were found loosely attached to the wall in multiple locations, and one handrail outside a resident room was unattached at one end and pulling away from the wall. Review of TELS work orders showed no report for the loose handrails, and the RM-D, MO-D, RN, and DON all confirmed the condition and that maintenance issues were expected to be reported through TELS.

No penalty information released
tooltip icon
The penalty, as released by CMS, applies to the entire inspection this citation is part of, covering all citations and f-tags issued, not just this specific f-tag. For the complete original report, please refer to the 'Details' section.
Loose Corridor Handrail
F
F0924 F924: Put firmly secured handrails on each side of hallways.
Short Summary

A corridor handrail in the west hall just past the main entrance was observed to be loose and easily pulled away from the wall. A PTA and the DON confirmed the rail was unsecured, and the deficiency was identified as affecting all residents who use handrails.

No penalty information released
tooltip icon
The penalty, as released by CMS, applies to the entire inspection this citation is part of, covering all citations and f-tags issued, not just this specific f-tag. For the complete original report, please refer to the 'Details' section.
Loose Handrail in First Floor Corridor
D
F0924 F924: Put firmly secured handrails on each side of hallways.
Short Summary

Loose Handrail in First Floor Corridor: A handrail on the front side of the nursing station was observed to be loose to touch during an inspection of the 1st floor nursing unit. A housekeeper confirmed it was not secured properly and said he had known about it since Thursday but was unsure whether maintenance had been notified. An RN supervisor confirmed that handrails should be securely affixed to the walls.

No penalty information released
tooltip icon
The penalty, as released by CMS, applies to the entire inspection this citation is part of, covering all citations and f-tags issued, not just this specific f-tag. For the complete original report, please refer to the 'Details' section.
Unsecured hallway handrail in North Station
D
F0924 F924: Put firmly secured handrails on each side of hallways.
Short Summary

Unsecured hallway handrail in North Station: The facility failed to keep a hallway handrail firmly secured to the corridor wall. An observation found the handrail was not secured, and the DON, MS, and IPN all stated it was not sturdy and should be secured for resident use. The MS reported that three of the mounts attaching the rail to the wall were broken.

No penalty information released
tooltip icon
The penalty, as released by CMS, applies to the entire inspection this citation is part of, covering all citations and f-tags issued, not just this specific f-tag. For the complete original report, please refer to the 'Details' section.
Corridor Missing Handrails Near Exposed Electrical Equipment
F
F0924 F924: Put firmly secured handrails on each side of hallways.
Short Summary

Corridor Missing Handrails Near Exposed Electrical Equipment: The facility failed to ensure corridor handrails were present on both sides. An egress corridor leading to the outdoor picnic and smoking areas contained newly installed generator-related electrical equipment, including transfer switches, manual disconnect switches, and electrical panels, without guards on the corridor side. Residents were observed using the corridor, and the missing handrails were noted on the same side as the equipment.

No penalty information released
tooltip icon
The penalty, as released by CMS, applies to the entire inspection this citation is part of, covering all citations and f-tags issued, not just this specific f-tag. For the complete original report, please refer to the 'Details' section.
Loose Handrail in Hall C
D
F0924 F924: Put firmly secured handrails on each side of hallways.
Short Summary

Loose Handrail in Hall C: A hallway handrail between Rooms C3 and C4 was observed to be loose and wobbly rather than firmly secured to the wall. The Maintenance Supervisor stated he was not aware of the issue unless it was written in the maintenance logbook, and the work order log showed no related work orders. The facility policy states maintenance must keep the building safe and operable at all times.

Inspection fine: $13,0705 days payment denial
tooltip icon
The penalty, as released by CMS, applies to the entire inspection this citation is part of, covering all citations and f-tags issued, not just this specific f-tag. For the complete original report, please refer to the 'Details' section.
Citation search

Search every citation & Plan of Correction

Go to search
Citation watch

Track new serious citations across Louisiana

Get a heads-up on the newest immediate-jeopardy (J–L) citations in Louisiana — where surveyors are focused right now.

Free · about one email a month

Trusted data from CMS and state health departments

Every citation, penalty and Plan of Correction is sourced from public CMS records (latest release August 26, 2026) and official state health department websites — never guesswork.

In your survey window? See what surveyors are citing.

The Survey-Prep Report maps your facility's risk from 12 months of CMS and state citation data — what's being cited around you and what to check first. $129 one-time.

Get the Survey-Prep Report
An unhandled error has occurred. Reload 🗙

Connection lost — reconnecting… We couldn't reconnect automatically. Please reload the page to continue.