F0700 F700: Try different approaches before using a bed rail. If a bed rail is needed, the facility must (1) assess a resident for safety risk; (2) review these risks and benefits with the resident/representative; (3) get informed consent; and (4) Correctly install and maintain the bed rail.
E

Failure to Conduct Bed Rail Assessments and Obtain Consent

Pacific Care CenterPacific, Missouri Survey Completed on 07-26-2024

Summary

The facility failed to complete necessary bed rail assessments and obtain informed consent for the use of bed rails for three residents out of a sample of 14, despite having a policy in place that requires these actions. The policy mandates staff to conduct bed rail observations, obtain consent, educate residents or their representatives on the risks and benefits, and develop a care plan for bed rail use. However, for Residents #21, #33, and #49, these steps were not followed, as evidenced by the lack of documented assessments and consents in their medical records. Resident #21 was assessed as requiring maximum assistance for various activities and had physician orders for bed rails, yet the medical record showed only one bed rail assessment and consent, with no further documentation. Observations confirmed the consistent use of bed rails without updated assessments or consents. Similarly, Resident #33, who was cognitively intact and required supervision for some activities, had no documented bed rail assessment or consent, despite observations showing the use of bed rails. Resident #49, with severe cognitive impairment, also lacked documentation for bed rail assessments and consents, although bed rails were observed in use. Interviews with facility staff revealed confusion and inconsistency regarding responsibilities for bed rail assessments and consent. LPN C, the maintenance person, the Nurse Consultant, and the Administrator provided conflicting information about who was responsible for these tasks and how often they should be completed. The maintenance person admitted to not performing entrapment measurements, and there was uncertainty about who should conduct these measurements. This lack of clarity and adherence to policy contributed to the deficiency in ensuring resident safety regarding bed rail use.

Penalty

No penalty information released
tooltip icon
The penalty, as released by CMS, applies to the entire inspection this citation is part of, covering all citations and f-tags issued, not just this specific f-tag. For the complete original report, please refer to the 'Details' section.

Resources

Below are regulatory guidelines relevant to this citation:

See other F0700 citations
Failure to Assess and Obtain Consent Before Bed Rail Use
D
F0700 F700: Try different approaches before using a bed rail. If a bed rail is needed, the facility must (1) assess a resident for safety risk; (2) review these risks and benefits with the resident/representative; (3) get informed consent; and (4) Correctly install and maintain the bed rail.
Short Summary

Failure to assess and obtain consent before bed rail use for two residents. Two cognitively intact residents with diagnoses including AFib, HTN, arthritis, CAD, and HF were observed with bed rails on their beds even though their MDSs indicated no bedrail use. Both records lacked a bedrail assessment, consent, and education, and the DON confirmed no assessment had been completed before the rails were installed.

No penalty information released
tooltip icon
The penalty, as released by CMS, applies to the entire inspection this citation is part of, covering all citations and f-tags issued, not just this specific f-tag. For the complete original report, please refer to the 'Details' section.
Failure to Assess Bed Rail Entrapment Risk and Mattress Settings
J
F0700 F700: Try different approaches before using a bed rail. If a bed rail is needed, the facility must (1) assess a resident for safety risk; (2) review these risks and benefits with the resident/representative; (3) get informed consent; and (4) Correctly install and maintain the bed rail.
Short Summary

A resident with severe cognitive impairment and total dependence for care fell from bed after an air mattress was set too high for the resident’s weight, causing the mattress to overinflate and push the resident into a siderail. The resident’s arm became trapped in the rail and the resident sustained neck and sternum injuries. The record also showed no siderail entrapment assessment for the resident, and multiple other residents with air mattresses and siderails also lacked documented side rail assessments.

No penalty information released
tooltip icon
The penalty, as released by CMS, applies to the entire inspection this citation is part of, covering all citations and f-tags issued, not just this specific f-tag. For the complete original report, please refer to the 'Details' section.
Failure to Reassess Bed Siderail Safety Led to Resident Injury
G
F0700 F700: Try different approaches before using a bed rail. If a bed rail is needed, the facility must (1) assess a resident for safety risk; (2) review these risks and benefits with the resident/representative; (3) get informed consent; and (4) Correctly install and maintain the bed rail.
Short Summary

A facility failed to complete ongoing reassessments of bed siderail safety for a resident with severe cognitive impairment and total dependence for bed mobility. The resident continued using the siderails for months without the required review, and later developed bruising and a traumatic posterior shoulder dislocation after the arm was reportedly caught in the rail. An internal investigation and later assessment found the siderails were unsafe and no longer indicated.

No penalty information released
tooltip icon
The penalty, as released by CMS, applies to the entire inspection this citation is part of, covering all citations and f-tags issued, not just this specific f-tag. For the complete original report, please refer to the 'Details' section.
Failure to Assess and Obtain Consent for Bed Rail Use
D
F0700 F700: Try different approaches before using a bed rail. If a bed rail is needed, the facility must (1) assess a resident for safety risk; (2) review these risks and benefits with the resident/representative; (3) get informed consent; and (4) Correctly install and maintain the bed rail.
Short Summary

Failure to Assess and Obtain Consent for Bed Rail Use: Two residents had one-quarter bed rails in place with physician orders for positioning and mobility, but the clinical record lacked documented bed rail safety assessments and signed informed consent. One resident had moderately impaired cognition and the other had severely impaired cognition; both were observed with the rails up and locked in place. The ADM and DON acknowledged the assessments and consents were missed, and staff stated the required documentation should have been completed before bed rail use.

No penalty information released
tooltip icon
The penalty, as released by CMS, applies to the entire inspection this citation is part of, covering all citations and f-tags issued, not just this specific f-tag. For the complete original report, please refer to the 'Details' section.
Failure to Document Alternatives and Monitor Bed Rail Use
D
F0700 F700: Try different approaches before using a bed rail. If a bed rail is needed, the facility must (1) assess a resident for safety risk; (2) review these risks and benefits with the resident/representative; (3) get informed consent; and (4) Correctly install and maintain the bed rail.
Short Summary

A resident with acute and chronic respiratory failure with hypoxia, Type 2 DM with hyperglycemia, generalized muscle weakness, and impaired cognition was placed in four locked bed rails for fall risk. The record showed only one alternative intervention, one-to-one activities and supervision, with no documented evidence explaining why it was ineffective, and the DON stated there was no documented active order for a low bed or other alternative. The resident was observed asleep with all four bed rails up and locked, and the care plan and active orders did not show monitoring for safe bed rail use.

No penalty information released
tooltip icon
The penalty, as released by CMS, applies to the entire inspection this citation is part of, covering all citations and f-tags issued, not just this specific f-tag. For the complete original report, please refer to the 'Details' section.
Failure to Assess Bed Rail Entrapment Risk
J
F0700 F700: Try different approaches before using a bed rail. If a bed rail is needed, the facility must (1) assess a resident for safety risk; (2) review these risks and benefits with the resident/representative; (3) get informed consent; and (4) Correctly install and maintain the bed rail.
Short Summary

Failure to Assess Bed Rail Entrapment Risk: A resident with severe cognitive impairment and multiple medical conditions was placed in a bed with assist rails without documented assessment for appropriateness, documented alternatives, or informed consent. Staff later found the resident with his head and neck trapped between the mattress and the assist bar, unresponsive and not breathing, and CPR was started before EMS transported him to the hospital. The resident was admitted with cardiac arrest and diffuse hypoxic injury and later expired.

No penalty information released
tooltip icon
The penalty, as released by CMS, applies to the entire inspection this citation is part of, covering all citations and f-tags issued, not just this specific f-tag. For the complete original report, please refer to the 'Details' section.
Citation search

Search every citation & Plan of Correction

Go to search
Citation watch

Track new serious citations across Missouri

Get a heads-up on the newest immediate-jeopardy (J–L) citations in Missouri — where surveyors are focused right now.

Free · about one email a month

Trusted data from CMS and state health departments

Every citation, penalty and Plan of Correction is sourced from public CMS records (latest release August 26, 2026) and official state health department websites — never guesswork.

In your survey window? See what surveyors are citing.

The Survey-Prep Report maps your facility's risk from 12 months of CMS and state citation data — what's being cited around you and what to check first. $129 one-time.

Get the Survey-Prep Report
An unhandled error has occurred. Reload 🗙

Connection lost — reconnecting… We couldn't reconnect automatically. Please reload the page to continue.